How Much Power Does a New Factory Need? Sizing the Transformer, HT Panel and DG Set

How a new factory works out its contract demand, transformer rating and DG set size, from connected load to maximum demand, with an illustrative worked example.

In short

  • A factory is sized on its maximum demand, not its connected load: the sum of every nameplate is almost always far more than the plant ever draws at once.
  • Transformers are rated in kVA, so the kilowatt demand must be divided by the power factor; correcting power factor to about 0.95 shrinks both the transformer and the electricity bill.
  • A distribution transformer is usually chosen to run at roughly 70–80% of its rating at maximum demand, which leaves room for growth and keeps losses low.
  • A DG set is sized for the loads that must survive an outage, and for the starting current of its largest motor, not for the whole plant.

The first electrical question on a new factory is usually asked in the wrong unit. The owner knows how many machines are coming and adds up their kilowatts. The distribution company wants a contract demand in kVA. The transformer is sold in kVA. The DG set is sold in kVA. And the monthly bill is driven by a demand figure that is neither of the first two.

Getting from one to the other is a short calculation, but every step in it is a judgement. Get it wrong on the high side and the plant pays for capacity it never uses, every month, for years. Get it wrong on the low side and the second production line has nowhere to plug in.

Connected load is not demand

Connected load is the sum of the rated power of everything wired to the system: every motor, heater, compressor, chiller, light and socket. It is the easiest number to produce and the least useful on its own, because no plant runs everything at full rating at the same moment.

Maximum demand is what the plant actually draws at its busiest, averaged over the metering interval the distribution company uses. The ratio between the two is the demand factor, and it is where most of the engineering judgement sits:

  • Standby equipment — the second pump, the spare compressor — is connected but, by design, not running.
  • Motors are rarely loaded to their full nameplate.
  • Batch processes, ovens and welding loads cycle on and off and seldom peak together.
  • Lighting, HVAC and process loads peak at different times of day and year.

For a typical manufacturing plant the demand factor commonly lands somewhere between a half and four-fifths of connected load. That is a range, not a rule — a continuous process plant sits at the top of it, a job shop full of intermittent machines near the bottom. The right figure comes from a load list that records, for each item, whether it runs continuously, intermittently or as standby.

From kilowatts to kVA

Machines consume real power, in kilowatts. Transformers, cables and DG sets have to carry the apparent power, in kVA, which includes the reactive current that motors draw to magnetise themselves. The bridge between them is the power factor:

kVA = kW ÷ power factor

A plant with a power factor of 0.8 needs 25% more transformer capacity than one at 1.0 to deliver the same kilowatts. An automatic power factor correction (APFC) panel, with capacitor banks switched in and out as the load changes, holds the plant near unity — and because the Maharashtra tariff rewards high-tension consumers for a good power factor and penalises a poor one, it usually pays for itself on the bill as well as on the transformer. We covered how it is measured and fixed in cutting a factory power bill.

Choosing the transformer

The transformer is sized from the maximum demand in kVA, with two allowances on top:

  1. Growth. If a second line, a new utility block or a future phase is planned, it belongs in the calculation now. A transformer is expensive to replace and the substation room around it is harder still to enlarge.
  2. Loading margin. A distribution transformer is normally chosen to run at roughly 70–80% of its rating at maximum demand. That keeps it cool, leaves headroom for motor starting and keeps it near its most efficient operating point.

The result is then rounded up to the next standard rating — 500, 630, 800, 1000, 1250, 1600, 2000 or 2500 kVA are the common steps. The primary voltage is set by the supply area, usually 11 kV, 22 kV or 33 kV, stepped down to 433 V for the plant. Distribution transformers in this range are covered by IS 1180, which also sets the energy efficiency levels they are labelled against; a higher efficiency level costs more to buy and less to run.

An illustrative worked example

The figures below are invented to show the method. They are not from a particular project.

StepCalculationResult
Connected loadSum of the load list1,500 kW
Maximum demand1,500 kW × 0.6 demand factor900 kW
Apparent power900 kW ÷ 0.95 corrected power factor≈ 950 kVA
Planned growth+ 20% for a second line≈ 1,140 kVA
Loading margin÷ 0.8 target loading≈ 1,425 kVA
TransformerNext standard rating1,600 kVA

The contract demand applied for with the distribution company is a separate decision. It is usually set near the expected maximum demand for the first years of operation rather than the transformer's full rating, because demand charges are billed against it whether the plant uses it or not, and it can be raised later as production grows.

The HT side: panel, metering and protection

Above a contract demand set by the distribution company's supply code, a factory takes its supply at high tension and owns the equipment that receives it. That typically means:

  • An HT panel — a vacuum circuit breaker or ring main unit with protection relays — between the incoming cable and the transformer.
  • Metering to the distribution company's specification, in a location it can access.
  • The transformer itself, outdoor on a plinth or indoor in a ventilated room, with oil containment if it is oil-filled.
  • An LT main panel that splits the supply to motor control centres, the utility block, lighting and the APFC panel.
  • Earthing and protection coordinated so that a fault trips the nearest breaker, not the whole plant.

The Electrical Inspectorate inspects and approves the installation before it can be energised, and the distribution company releases the connection after that. Both run on their own timelines, which is why the electrical approvals belong at the start of a factory programme, not at the end.

Sizing the DG set

A DG set is not a second transformer. It is sized for a decision about which loads must keep running when the grid fails:

  • Essential loads — fire pumps on electric drive, emergency lighting, controls, IT, critical process cooling, and whatever part of production cannot be stopped mid-batch.
  • The largest motor start. A motor started direct-on-line draws several times its running current for a few seconds. The DG must ride through that without its voltage collapsing, which often sets the size more than the running load does. Soft starters and VFDs reduce it.
  • Sensible loading. A diesel generator runs best between roughly half and four-fifths of its rating. A set that idles at light load for long periods carbons up; one that runs near full rating has nothing left for a motor start.

New DG sets up to 800 kW must meet the CPCB IV+ emission norms, and the set needs its own exhaust stack, fuel storage and acoustic enclosure — all of which take space in the layout. Where more than one set is needed, a synchronising panel lets them share load and run only as many as the demand requires.

Questions buyers ask

Can we start with a smaller transformer and upgrade later?

You can, but the substation is the expensive part to change. A common middle path is to build the transformer plinth, HT panel and cable routes for the final rating and install the smaller transformer first, so the upgrade is a swap rather than a rebuild.

Is one large transformer better than two smaller ones?

Two transformers cost more but let the plant keep running on one while the other is maintained or has failed. For plants where an outage stops a continuous process, the redundancy is usually worth it.

How long do electrical approvals take?

It depends on the supply area and the distribution company's workload. What is predictable is that the application, the Electrical Inspectorate's inspection and the release of supply are sequential — none can start until the one before is complete — so they should be started as soon as the load list is firm.

Do we need an HT supply at all?

That is set by the supply code: below a certain contract demand, a plant can be supplied at low tension from the distribution company's own transformer. Most new factories with significant motor load cross that threshold.

Delivered as one scope

Transformer installation, HT and LT panels, power distribution, APFC panels, DG sets and electrical commissioning are part of the electrical infrastructure VPSTEC delivers, alongside the plant layout that decides where the substation, DG yard and cable routes go. Sizing them together — from the same load list, against the same layout — is what stops the transformer, the DG set and the bill from each being right on their own and wrong together.